SW Johnson County Interchange

Project Timeline

Fall 2009

Public Meeting will be conducted to review project goals and preliminary alternatives.

Fall 2009 - Winter 2009

Develop ranking criteria for alternatives that meet project goals.

Winter 2009 - Spring 2010

An alternative will be selected and an Environmental Assessment will be completed on the alternative.

Spring 2010 - Summer 2010

The Environmental Assessment report will be published.

Summer 2010 - Fall 2010

Public Meeting will be conducted to review the alternative and the associated Environmental Assessment.

Fall 2010 - Winter 2010

The Federal Highway Administration reviews Environmental Assesment.